LAWAS: The newly completed Lawas Town Bridge has been recognised by the Malaysia Book of Records (MBOR) for having the Longest Decorative Cable Structure Installed on a Balanced Cantilever Bridge in Malaysia.
Regional Corridor Development Authority’s (RECODA) Chief Executive Officer, Datuk Ismawi Ismuni said the recognition reflected the distinctive design of the bridge, which is developed to serve not only as an infrastructure link but also as an iconic landmark representing Lawas.
He said the bridge’s design underwent extensive refinement following a challenge by Deputy Premier Datuk Amar Awang Tengah Ali Hasan to make it one of the most beautiful bridges in Sarawak.
“Initially, the bridge was planned as a conventional balanced cantilever bridge. However, Datuk Amar Awang Tengah challenged RECODA to make it among the most beautiful bridges in Sarawak.
“He was personally involved in refining and improving the design until we achieved what we see today,” he said in his welcoming speech during the launch of the Lawas Town Bridge here on Wednesday (Nov. 18).
Ismawi said more than 10 engagement sessions were held between RECODA, the consultant team and Awang Tengah to examine every design detail, from the shape of the towers to the decorative features at their peaks.
Architects were also brought into the consultancy team to help refine the design, an approach he described as uncommon in bridge construction.
The 642-metre balanced cantilever bridge, located on the eastern side of Lawas Town, was developed by RECODA under the Northern Region Development Agency (NRDA), which was entrusted with RM1.5 billion in allocations for development projects.
The RM149.86-million project was awarded to Pekerjaan Piasau Konkerit Sdn Bhd through an open tender on April 28, 2022, with construction beginning in May that year.
The bridge features four gateway towers, each standing 44.3 metres tall, topped with decorative domes and fitted with suspended cables illuminated by LED lighting.
During construction, the project encountered unexpected soil movement, requiring the foundation design to be reviewed and adjusted according to actual site conditions.
Ismawi said geological experts were also engaged to ensure the stability, strength and safety of the bridge structure.
Despite the challenges, the project obtained its Certificate of Practical Completion (CPC) on October 15, 2026, nearly three months ahead of its expected completion date.
He said the successful delivery of the project was made possible through the cooperation of various government agencies, consultants, contractors and the local community.
Meanwhile, Ismawi said another RECODA project, the Northern Coastal Highway (NCH), had also received recognition from MBOR as Malaysia’s largest 3D-printed civil infrastructure model.
The highway project was also recognised at the Green and Geopark Excellence Awards (GAGA) 2026, where RECODA received the Aspiring Sustainability Infrastructure Project award on October 6.
He said the recognitions are meaningful milestones for RECODA and should be shared with the people of Lawas and Sarawak.
“These recognitions do not belong to us alone, but to the entire Lawas community and the people of Sarawak,” he said.
The Lawas Town Bridge project was approved by Premier Datuk Patinggi Tan Sri Abang Johari Tun Openg as one of the projects funded under the RM1.5-billion allocation entrusted to NRDA.