LAWAS: Limbang and Lawas have been fully integrated into Sarawak’s electricity grid, strengthening power supply reliability in the Northern Region while reducing dependence on diesel-powered generation.
The connection, completed in July this year, allows both districts to benefit from Sarawak’s electricity supply system, which is largely powered by hydroelectric generation, the state’s main source of renewable energy.
The symbolic launch of the 275kV grid connection to Limbang and Lawas was officiated by Premier Datuk Patinggi Tan Sri Abang Johari Tun Openg at Trusan here today, in conjunction with the groundbreaking ceremony for the new Trusan Water Treatment Plant.
Sarawak Energy’s Group Chief Executive Officer, Datuk Ruslan Abdul Ghani, said the successful integration of the two districts into the state grid marked a significant milestone in improving electricity supply reliability in the Northern Region.
“With Lawas and Limbang now connected to the Sarawak electricity grid, the resilience of the electricity supply system is strengthened, ensuring a more stable and reliable supply for consumers.
“At the same time, this infrastructure provides a stronger foundation to meet growing energy demand and support local economic development.
“It also opens up opportunities to plan for future electricity supply expansion to rural areas such as Batu Danau and Ulu Medamit,” he said, in a statement by Sarawak Energy.
Ruslan said the development reflected Sarawak Energy’s commitment to providing reliable, sustainable and affordable electricity to support economic growth and the well-being of communities throughout Sarawak.
Lawas was first connected to the Sarawak electricity grid following the commissioning of its transmission infrastructure in November 2025, with electricity supply from the grid commencing on December 4 that year.
Limbang followed on July 31, 2026, with the commissioning of the 275kV Limbang Town Main Intake Substation (PMU) and activation of the 275kV Bunut-Medamit-Limbang transmission line.
The Limbang grid connection project involved approximately 228 kilometres of 275kV transmission lines, supported by transmission towers and monopoles, stretching from Bunut through Medamit to the Limbang Town Main Intake Substation.