New RM96.79m school to ease pressure on Kapit secondary schools

Facebook
X
WhatsApp
Telegram
Email
Nanta (left) attends the groundbreaking ceremony for the project. Photo: UKAS

LET’S READ SUARA SARAWAK/ NEW SARAWAK TRIBUNE E-PAPER FOR FREE AS ​​EARLY AS 2 AM EVERY DAY. CLICK LINK

KAPIT: The construction of the new RM96.79 million SMK Bukit Goram is expected to ease pressure on existing secondary schools in Kapit Division by providing additional capacity for 1,115 students.

Kapit MP Datuk Seri Alexander Nanta Linggi said the new school is necessary as existing secondary schools in the division are increasingly struggling to accommodate growing student enrolment.

He said the school is designed to cater for 1,080 mainstream students and 35 students with special educational needs (SEN).

“The construction of this new school is very much needed as the capacity of existing secondary schools is becoming insufficient to meet the demand for student enrolment,” he said during the Letter of Acceptance (SST) handover and groundbreaking ceremony for the project at Kampung Kemarau here yesterday (Nov 20).

Nanta, who is also Works Minister, added that savings of about RM40 million from the project allocation, compared with the tender price, could potentially be channelled towards the construction of teachers’ quarters and a student hostel, subject to approval from the relevant ministries.

He expressed hope that the contractor could complete the project six months ahead of schedule, taking into account its previous project delivery performance.

The project is scheduled to take 182 weeks to complete, with its completion date set for May 16, 2030.

Developed on a 7.19-hectare site, the school will comprise an administration block, an academic block with 36 classrooms, a secondary Integrated Special Education Programme (PPKI) block with five classrooms, a canteen, school hall, toilets and other supporting facilities.

Meanwhile, Public Works Department Malaysia director-general Datuk Ibrahim Esa stressed that all parties involved must ensure the project is delivered according to the stipulated timeline, specifications and quality standards.

He reminded the contractor and project director to discharge their responsibilities professionally and with integrity, while closely monitoring construction progress and identifying potential site issues early to prevent delays.

The project also places emphasis on achieving zero sick projects and early completion through close cooperation between the Education Ministry, Works Ministry, Public Works Department and the contractor.